Newark, New Jersey · Building since 2016 General contractor · Construction manager · Design-builder CareersNewsroomPrequalifyProject map
Energy · Energy Infrastructure

Built for the turnaround window.

Green hydrogen plants, process expansions, pre-assembled modules, pipe racks and plant upgrades, delivered by crews who know that every hour of a turnaround is an hour of lost production.

What owners need from us.

01

The window is fixed

A planned turnaround has a start date and a restart date. Every lift, tie-in and hydrotest has to fit inside it, with float held for what the opened equipment reveals.

02

Hazards are live

Hot work next to operating units, confined spaces and line breaks on systems that held hydrocarbons yesterday. Permits, gas testing and isolation are part of the schedule, not an afterthought.

03

Field hours carry risk

Every weld made inside the fence adds congestion and exposure. Owners want as much work as possible done off site, then set and connected fast.

Energy Infrastructure

What we build.

  1. 01

    Hydrogen and process units

    Electrolyzer, compression and storage plants, new and debottlenecked units, foundations, steel, equipment setting and tie-ins to live headers.

  2. 02

    Pre-assembled modules

    Pipe rack and equipment modules fabricated, dressed and tested in the yard, then shipped and set on prepared foundations.

  3. 03

    Turnaround and tie-in work

    Planned outages with pre-staged spools, hot-tap and tie-in packages, and round-the-clock shifts to the restart date.

  4. 04

    Terminals and midstream facilities

    Tank farms, loading racks, compressor and pump stations, and the piping and electrical that connect them.

How we deliver here.

The capabilities owners in this market rely on most.

Engineer-Procure-Construct (EPC)Deliver

Lump-sum EPC with one team carrying engineering, long-lead procurement and field execution.

Design-Manufacture-InstallDeliver

Modules fabricated in our yard so field hours inside the fence drop and the turnaround stays short.

Self-Performed ConstructionBuild

Our own crews for foundations, steel erection, rigging and pipe installation, under one safety program.

Virtual Design & ConstructionPlan

Laser-scanned existing plant and 3D models so new spools and modules fit the first time they are set.

In practice · Green Hydrogen Production Facility

Renewable power in, clean hydrogen out.

The Green Hydrogen Production Facility was delivered under an EPC contract as a first-of-its-kind plant for its owner. Electrolyzer, compression and storage modules were built and pressure tested off site, then set on prepared foundations and connected to the incoming renewable power. Our team built the plant network, gas detection and safety controls with the process systems, and every loop was proven before the first hydrogen was made.

20 MW
Electrolysis
EPC
Delivery
2025
Completed

Questions owners ask us.

How do you protect a turnaround schedule?

We build the turnaround plan with operations months ahead. Spools, valves and modules are on site and checked before shutdown, tie-in packages are walked down, and the critical path is reviewed every shift.

How do you manage work next to operating units?

Every task runs under the owner’s permit system with job hazard analysis, continuous gas monitoring where required and verified isolation before any line is opened.

Why move work into modules?

Work done in a fabrication yard is safer, easier to inspect and not exposed to plant congestion or weather. It shortens the time crews spend inside the fence and the time the unit is down.

Energy Infrastructure

Planning a energy infrastructure project?

Share the project, the site and the date that matters. A senior builder will come back to you within one business day.